This site is for recording maintenance records of the Little Cayman Research Centre (Central Caribbean Marine Institute) & NOAA ICON/CREWS station for data management purposes. Please update this blog whenever new operations are performed in the field, so that NOAA/AOML can coordinate data management efforts with the Little Cayman ICON/CREWS field efforts.
Thursday, October 11, 2012
Friday, June 15, 2012
Full Validation and Clean 13 June 2012 and Nav light replacement
After the Ground Truth sensor was installed at 7:50, a cleaning session involving 7 divers started at 9:00. All the instruments, chains, lines and pole were cleaned. Bio-fouling was moderate, probably due to us cleaning a the station a couple of weeks late. Cleaning finished at 11:30 and the GT Sensor removed at 2pm.
We tried to replace the anodes on the chain but between the two sizes we have, one is two big and another two small. We will source from somewhere else. Three of the chains do now have new anodes. Anodes and filters on the instruments were also cleaned and checked and are in good condition. While we were out there we mounted a YSI pH instrument to the side of the pole one meter below the surface. This will be collected in 2 weeks and the data used for one of CCMI's Ocean Acidification Manipulative studies.
A few weeks ago the Navigation Light on the Station stopped working, yesterday (June 14th) we replaced the light with a Carmanah M650, a newer model of the M601 which was installed before. ( please see photo)
We tried to replace the anodes on the chain but between the two sizes we have, one is two big and another two small. We will source from somewhere else. Three of the chains do now have new anodes. Anodes and filters on the instruments were also cleaned and checked and are in good condition. While we were out there we mounted a YSI pH instrument to the side of the pole one meter below the surface. This will be collected in 2 weeks and the data used for one of CCMI's Ocean Acidification Manipulative studies.
Monday, May 07, 2012
Full Validation and Clean 2 May 2012
Due to an unexpected Nor'wester our cleaning of the CREWS station was postponed to and completed on 2nd May. 3 divers started cleaning at 9:15 and finished at 11:00. The GT sensor was installed at 7:50am and removed at 1:30. Strong current made cleaning difficult near the surface but all was completed. The sensors, lines, chain, and stick looked to be in good condition with low biofouling, no change on the orientation of the station. It was noted that there was minimal fire coral present before cleaning.
Thursday, March 22, 2012
Full Validation and Clean 21/Mar/2012
Yesterday 4 divers completed a full validation and clean. The station had low to moderate biofouling. A couple of patches of fire coral were noted as we have not had any on the station over the winter, we removed all that we could find, lets see if we have more as the water temperature increases. The Gt Sensor was installed at 8:15am and removed at 1:05pm, we commenced cleaning of the instruments at 11:20 and completed the rest of the station over the next 90 minutes. We also removed the 4 temperature leveloggers form the station and are returning them to Miami for calibration, they have been on the station for over a year. Everything else on the station looked normal.
Tuesday, February 21, 2012
Full Validation and Clean 11/Feb/2012
The CREWS station received its second cleaning of the year. All the sensors, chains, lines and pole had limited biofouling. The whole station was cleaned by 4 divers after the GT sensor was installed at 8am, the cleaning commenced at 9:30 for 90 minutes. The GT sensor was then removed around 1:20pm. Everything looked in place, no changes were obvious since our last visit.
Subscribe to:
Posts (Atom)