Wednesday, July 22, 2009

Electronics Installation

Station electronics were installed on the pylon on Tuesday, July 21st and Wednesday, July 22nd, 2009. Work was carried out by a team consisting of Drs. Jim Hendee and Derek Manzello (NOAA/AOML in Miami, FL), Dr. Jennifer Dupont (NOAA/OAR International Activities Office in Silver Spring, MD), Lowell Forbes (CCMI/Little Cayman Research Centre) and myself, Mike Jankulak (University of Miami).

Monday evening and Tuesday morning, all electronics components were assembled on the workbench as a final test of equipment, wiring and programming (see photo, left, of the "brain," or control unit, featuring the datalogger and GOES transmitter). Work at the pylon began Tuesday afternoon, with the installation of the temporary climbing rungs and safety lines. Next, the underwater cables were run from the waterline, through the internal conduits and up into the top chamber -- the cable for the underwater light sensor was run through the southernmost conduit and the other two cables (for the CTD, or conductivity-temperature-depth sensor, and the CT, or conductivity-temperature sensor) were run through the second, northernmost conduit.

The movement of heavy equipment was temporarily halted so that divers could install the underwater instruments and mounting brackets (see photo at right). During this period, the wiring of these cables to their connectors was completed at the top of the pylon, and the cable attachment point for the GOES transmitter's satellite antenna was checked for possible saltwater damage from its brief immersion during pylon installation. When the underwater work was complete, the station's two rechargeable batteries were hoisted aloft and installed in the upper chamber, bringing an end to the day's work.

Wednesday morning, work at the pylon resumed. Two of the three aerial instrument masts were installed, one holding the station's Vaisala WXT520 (Weather Transmitter, providing data for winds, air temperature, barometric pressure, relative humidity and precipitation), complete with bird deterrent spikes, and the other other holding the RM Young Wind Monitor (a marine-grade anemometer) and Electronic Compass. A smaller mount holding the GOES transmitter's GPS antenna was attached off the side of one of the main masts which hold the satellite transmitter antenna and the navigation light. The third mast was temporarily mounted to measure its orientation (approximately 20 degrees north of due east) in preparation for installation of the surface light sensor.

Back on the boat, the surface light sensor was attached to its mount and the mast grounding wires were prepared for installation. The afternoon pylon work consisted of installing the standalone air temperature sensor, which is positioned behind one of the north-facing solar panels, and the surface light sensor on its aluminum mast. After all cables were run into the pylon's upper chamber and their connectors securely attached, it was time to install the "brain," or control unit. This package of electronics was carefully hoisted aloft and inserted into the upper chamber, taking care to lower it past the protruding wires and connectors still to be attached.

Once the "brain" was set in place, all of its connections were made: grounding wire, batteries (two), solar panels (five), transmitter satellite antenna, transmitter GPS antenna, air temperature sensor, wind monitor, electronic compass, Vaisala weather transmitter, surface light sensor, underwater light sensor, CTD and CT. At this point the station's power switch was placed in the ON position (see related blog post).

Boatside once more, a laptop was connected to an RF401 radio transmitter (powered off the boat's battery) to communicate with the newly-powered station and confirm that all instruments were functional. All equipment was confirmed to be operating as expected, except the satellite transmitter (which would be confirmed operational later that day, after several hours of transmissions were received) and the solar panels (whose correct operation is inferred from the daily rise in station battery voltages, which would not be confirmed until the next morning's sunlight). There remained only the "tidying" phase of the operation: divers/snorkelers retrieved the "groundtruth" CT (which is only connected to the station during maintenance and cleaning), clipped off the ends of all cable ties, and attached a rubber sheet to protect the underwater cables at the waterline. Aloft, all of the external openings to the electronics chamber were plugged with aquaseal and a dozen dessicant packs were left inside before closing it up. The last important step was the installation of the grounding wires to connect all of the station's aluminum masts to one another, to the lightning diffuser brush (the station's highest point), to the station electronics, and to a zinc plate on the outside of the pylon near the ocean floor. When all work was complete, the station's safety lines and climbing rungs were removed.

The team is extremely grateful to the staff of and visitors to the Little Cayman Research Centre for their hard work and warm welcome, including but not limited to Dr. Carrie Manfrino, Lowell Forbes, Jon Clamp and Brenda Gadd. Myfanwy Rowlands is also to be commended for her amazing photo and video footage from the operation.

Photo credits for this post: J. Dupont (underwater work) and M. Jankulak (control unit)

Up & Down


After arrival at the station, Mike Jankulak navigates up and down via the aluminum rungs as adjustments are made to cabling and instrument installation.

Friday, July 10, 2009

Squid Buddies


For some reason, the squid love the ICON/CREWS stations.

Photo by Myfanwy Rowlands

Wednesday, July 08, 2009

The "Stick" is Installed!

The fifth ICON Station is vertical! On July 7-8, 2009, the CREWS/ICON pylon was erected at the pin/plate site offshore of LCRC. Led by CCMI staff member Jon Clamp, a composite dive team of Cayman Islands Department of Environment personnel and local divers secured the Pylon to the previously installed anchoring pins through the use of lift bags and manual methods. Technical advice and training on deployment procedures was provided by NOAA/AOML oceanographer Jules Craynock. Construction divers included D.O.E Keith Neale, Delwyn McLaughlin, Robert Walton, and Wade Moore of Power and Light, Little Cayman. CCMI staff member Lowell Forbes assisted Jon Clamp in the rigging and tensioning of the pylon structure. U/W photographic coverage of the operation was conducted by Myfanwy Rowlands (on a scholarship from the Our World-Underwater Scholarship Society) and CCMI staff member Claire Dell. The pylon was properly secured with a blinking navigation light visible from dusk to dawn and at a distance of rougly 3 nautical miles. Planned Instrumentation installation on the pylon and final transmitting of oceanographic data will be for July 21-23, 2009.

Jules Craynock
Photos by Myfanwy Rowlands

Friday, May 01, 2009

LCYI2 Island Prep



On April 27, 2009 Manuel Collazo of the University of Miami RSMAS Machine Shop and myself, Michael Shoemaker of AOML OCD, began the process of preparing the ICON station designated LCYI2 for installation near the Little Cayman Research Center. Our first step was the transportation of the Pylon from the research station down to the salt dock by flat bed trailer where it would be leaded and staged for deployment. Our next step on April 28 was the installation of the masts which support the navigation light, GOES antenna and the lightning brush. When done with the masts we then tackled the solar panel installation. On April 29 the final part of the preparation was performed which called for drilling out a section at the base of the pylon and mixing 750lbs of lead shot with epoxy resin to fill the ballast chamber at the bottom. We then patched the area with tri-axial Fiberglass cloth and compressed it with peel ply for an overnight cure. Our final day's work on April 30 consisted of removal of the peel ply and painting the section with anti-fouling paint then moving up to the top end of the pylon and applying reflective tape and designator lettering.

Photos by Claire Dell

Wednesday, April 09, 2008

Pins and Plate Installation April 7 - 9, 2008

On Monday of this week Jules Craynock and Nancy Ash of NOAA/AOML performed the initial u/w layout of the center base plate and 8 peripheral pins offshore of Little Cayman Research Centre (LCRC). Positioned in hardpan bedrock in the fore reef zone on the shallow terrace that surrounds the island, the pylon will be deployed approximately .25 miles northeast of the LCRC. From an initial base plate position of 19º 41.934’ N, 080º 03.632’ W and a depth of 22 fsw, the peripheral pin positions were marked at a radius of 30ft. around the center base plate position for drilling the next day. Later on Monday the crew of the R/V Sea Keeper arrived at LCCI. The Sea Keeper is operated by the Cayman Islands Department of Environment as a superb, fully capable coastal service vessel. Led by Tim Austin, the crew included Keith Neale and Delwin McLauglin.

On Tuesday, joining the crew for the drilling operation was also Little Cayman Marine Officer Hank Blagen, and Carrie Manfrino and Jon Clamp of CCMI. All participants embarked with calm seas to the offshore site aboard the R/V Sea Keeper. A two- point mooring was used to place the stern of the vessel near to the intended base plate position so that the hydraulic drilling rig could be deployed. After drilling five holes for the 18” base plate pins, 8 holes were then drilled at the peripheral positions to install stainless steel T- pins. After filling the pinning holes with concrete, the base plate was leveled and pinned with stainless steel rods. The peripheral pins were also installed with a concrete fill. Seas remained calm and good conditions enabled rapid progress. Of particular note was the excellent cooperation and great working spirit to be found with our R/V Sea Keeper colleagues.

After allowing the concrete to set overnight, the site was revisited and bearing and depth measurements retaken. The successful installation site was marked with a small orange subsurface buoy.

Posted by Jules Craynock




Fantail briefing before start of operations.


Overhead view of hydraulic drilling rig aboard R/V Sea Keeper attended by Keith Neale.

NOAA Oceanographer Jules Craynock and C.I. Department of Environment Assistant Director - Research and Assessment, discussing the base plate mounting.
Deploying the drill from the R/V Sea Keeper.






Expert Driller, Delwin McLaughin boring 7/8” pilot holes for the base plate installation.

Thursday, November 15, 2007

Memorandum of Understanding

The Memorandum of Understanding between NOAA and the Little Cayman Research Center (Central Caribbean Marine Institute) was finally signed! Construction of the station will soon begin.

Jim